Screengrabs of video showing excavation near Sheshnag Lake In South Kashmir's Pahalgam area. Photo/ Shared on X @buttkout
News Analysis

Road to Sheshnag: The Gap Between BRO’s ‘Widening Track’ and 2024 ‘Highway Plan’

Heavy machinery at one of Kashmir's 14 high-risk glacial lakes raises flood fears, while the government's road plan says no environmental clearance is needed

KT News Desk

SRINAGAR: Heavy machinery is cutting into the slopes around Sheshnag, a glacial lake at about 11,730 feet on the Amarnath pilgrimage route. The Border Roads Organisation (BRO) says it is only widening existing tracks. Government planning documents, however, describe something much larger - a two-lane national highway, with a 10.8 km tunnel, running past this lake to Baltal.

The work came to light when a video of an excavator at the lake went viral last week, triggering public outrage. Political leaders strongly criticized the presence of JCB machine near the lake. The social media was abuzz with concerns of devastation at the pristine heights of the Himalayas.

More than a day later, the BRO issued a statement from Jammu calling the social media claims misleading.

Sheshnag is not an ordinary lake. It is one of 14 high-risk glacial lakes identified by the Jammu and Kashmir government's Focused GLOF Monitoring Committee. The state disaster department has mounted expeditions to it to assess outburst-flood hazard.

The reaction cut across party lines. CPI(M) legislator Yousuf Tarigami told reporters that heavy machinery on such terrain was "an invitation to disaster" and demanded an environmental impact assessment. Mirwaiz Umar Farooq, Apni Party chief Altaf Bukhari, National Conference MP Mian Altaf and former MP Ruhullah Mehdi also asked for the work to stop. The administration stopped Mehbooba Mufti, former chief minister, from visiting the site.

Official speak, distortions and half-truths

The BRO statement of November 23, posted on X, names no clearance, no approving authority, no width, no length of track and no officer. It claims compliance without showing any in its six sentences.

It maintains the work was carried out in compliance with "all applicable safety norms and environmental safeguards." The statement does not say which norms apply. It cites no forest diversion approval, no wildlife board permission, no environmental impact assessment and no glacial-hazard study. No permit or approving authority was named anywhere in the BRO's response.

It mentions, "claims about new works are incorrect." In the very next sentence, the statement says the BRO "has started widening of tracks". Widening a mountain path with an excavator is new work. The denial rests on a distinction between a track and a road that the BRO never defines.

It states that the works are "confined to the existing tracks." This is the most misleading line. The government's own highway plan runs along the same foot trail.

The January 2024 detailed project report (DPR) for NH-501 says the new road follows the traditional yatra route through Chandanwari, Pissu Top, Zojibal, Sheshnag, Ganesh Top and Panchtarni. On this alignment, "existing track" and "future highway" describe the same strip of mountain.

The BRO statement states it is “widening the tracks as prescribed." Prescribed by whom, and to what width? The BRO has done this before. In 2024, its director general said the tracks, once three to four feet wide, had been widened to 12 feet. Parts of the Baltal track were taken to 15 feet.

It also claims to ensure "safe disposal of excavated material." The statement does not say where the debris goes. Beside a lake ringed by moraine and steep slopes, that is the central question. No dumping site has been disclosed.

The BRO's record on such denials has been shoddy. On November 10, 2023 it called reports that vehicles would soon reach the cave "factually incorrect". Within days, its own Project Beacon posted video of a truck and a pickup reaching the cave from Domail.

The statement also omits what it is part of. It does not mention NH-501, the National Highways and Infrastructure Development Corporation (NHIDCL), the Sheshnag tunnel or the cost. It does not mention the lake's high-risk status. It frames the work as routine "post-Yatra" maintenance, done in November when pilgrims and most observers have left.

The clearance question

No environmental clearance has been made public for any part of the road past Chandanwari. The project's own planning document explains why: it argues none is needed.

The detailed project report (DPR) for "2/4 laning of Khanabal to Baltal section on NH-501" was prepared by Redecon (India) Pvt Ltd for NHIDCL, under the Ministry of Road Transport and Highways, and is dated January 2024.

Its environment chapter is ten pages long. Much of it covers road markings and traffic signs. Five claims in it do not hold up.

1.     Category B, and also exempt: The DPR classifies the project as Category B under the EIA Notification, 2006, which would mean state-level appraisal. Its conclusion then says the project is exempt from environmental clearance altogether. It cannot be both.

2.     The exemption covers only part of the road: A 2013 amendment requires clearance only for national highway expansions over 100 km. The DPR's assessment covers just 39.45 km of brownfield road. The 32.6 km greenfield stretch past Chandanwari, which the DPR itself calls road where "there is no existing road", is parked "under different project package". Splitting highways into sub-100 km packages is itself unsettled. In January 2021, the Supreme Court cleared a Tamil Nadu highway split this way, but directed the environment ministry to set up an expert committee to examine whether such segmentation is permissible at all. A new national highway on fresh alignment is listed separately in the EIA schedule and needs prior clearance.

3.     No wildlife sanctuary within 5 km: The DPR says no sanctuary lies within 5 km, so no wildlife board permission is required. Yet the Overa-Aru Wildlife Sanctuary forms the backdrop of Pahalgam, which the road bypasses. The Centre's draft eco-sensitive zone notification said that zone's boundary runs along Pahalgam and Nunwan camp. The highway's far end, Baltal, sits beside the Thajwas wildlife sanctuary, covered by the same ESZ notification.

4.     No protected or reserve forest: The DPR says so, then states that forest clearance is required and the area is "under scrutiny". A 2017 civil society study found every yatra camp sits on forest land, including about 12.4 hectares at Sheshnag. It found the state Forest Advisory Committee had discussed track widening to the cave in 2013 but never approved it.

5.     Silence on the mountain: The environment chapter does not mention Sheshnag lake, glaciers, glacial-lake floods, or seismic risk. Elsewhere, the same DPR concedes the greenfield stretch is avalanche- and landslide-prone, rising above 4,000 metres.

There is a second legal route around scrutiny. The Forest (Conservation) Amendment Act, 2023 removed from the law's purview forest land within 100 km of the Line of Control used for "strategic linear" projects. The DPR pitches NH-501 as a new strategic route to Ladakh. Whether the government has invoked this exemption for the Sheshnag work is not known. The BRO, an organisation under the Ministry of Defence, has not clarified.

For the narrower track work, the BRO has cited Supreme Court directions in a 2012 case on yatra facilities. Those directions sought wider tracks for pedestrians and ponies, with environmental concerns kept in view. They did not authorise a road for vehicles, or exempt anyone from forest and wildlife law.

Why build a highway for a pilgrimage that lasts weeks?

Originally a two-week yatra, the cave is now reachable for 45-60 days each summer. The route past Chandanwari is under snow for most of the year. The DPR itself says this greenfield stretch "is closed for many months". So why a two-lane highway?

The DPR gives three reasons. First, pilgrims could reach the cave and return to base camp in a day, instead of three to seven. Second, it cites deaths from altitude sickness, flash floods and avalanches, and militant threats. Third, and least discussed, it describes NH-501 as part of a "completely new and shortest route" to Ladakh, bypassing the Banihal–Srinagar highway and "boosting the strategical" value of the region. It also notes the road's start lies near the Bijbehara emergency airstrip, useful "during the hostile period".

The safety argument can cut both ways. A road delivers more people, faster, to an altitude where they have not acclimatised. Pilgrim numbers have already risen from tens of thousands to over five lakh in 2024. The 2026 yatra ran 57 days with no announced upper limit. Until 1996, the yatra lasted 15 to 19 days. The Sengupta report noted that the most auspicious days were Raksha Bandhan and the ten before it.

The idea of a road to the cave is old, and it has been rejected before. In 1999, the Supreme Court accepted the state's argument that the high routes could not be kept open year-round. In 2016, a Vishwa Hindu Parishad activist in Jammu told researchers of a planned series of tunnels from Chandanwari to Panchtarni, linking to the Zojila tunnel. He said it had strategic ramifications.

Timeline of the three-decades of a road to the Amarnath Cave Shrine in Kashmir, Jammu & Kashmir.

Read as a sequence, the November work is not a one-off repair. It is one step in a plan pursued for three decades and denied at almost every stage.

Mapping the ongoing work on Sengupta report

The only full official inquiry into the yatra's limits pointed the other way. After about 243 people died in a blizzard in August 1996, the Union government appointed former bureaucrat Nitish K. Sengupta to investigate. His December 1996 report treated the pilgrimage as high-altitude mountaineering. It saw the narrow track as a reason to limit numbers, not a problem to engineer away.

What the Sengupta report recommended and what happened.

In 2004, the Home Minister told the Lok Sabha that Sengupta's limits would stay until the tracks were widened and strengthened. That condition came from a later committee under Lt Gen J.R. Mukherjee. It explains the logic now at work: widen the track, and the case for more pilgrims follows. In 2005, Governor S.K. Sinha argued for lifting the cap on exactly this basis.

Sengupta's report was not an environmental document. The 2017 study ‘Amarnath: A militarized pilgrimage’ by the Jammu Kashmir Coalition of Civil Society notes that it, like the Supreme Court later, mostly measured capacity by the track and pilgrim safety. Even so, its limits were never applied. The same study says none of the recommendations of the Sengupta, Mukherjee or 2006 Pollution Control Board reports on numbers were implemented.

Rights activist Gautam Navlakha made the same point in 2015, citing Sengupta's 3,000-a-day figure.

Is this the right model for the Himalaya?

The model on show at Sheshnag is the one the Himalaya has paid for repeatedly: widen first, assess later, and let capacity follow the concrete. The terrain gives little margin for it.

Sheshnag is fed by glaciers and hemmed in by loose moraine. Glacial-lake outburst floods have struck Kedarnath in 2013, Chamoli in 2021, Sikkim in 2023 and Dharali in 2025, as the National Disaster Management Authority has acknowledged. The state is still installing early warning systems at its high-risk lakes. Cutting the slopes around one of them before that work is finished reverses the order of caution.

Most of the Kashmir valley lies in seismic zone IV. The JKCCS–EQUATIONS study notes that where glaciers retreat, rock walls lose support and slopes destabilise. Kolahoi, the largest glacier feeding the Lidder, has receded sharply over five decades. The DPR itself calls the greenfield stretch avalanche- and landslide-prone.

The Lidder, which drains Sheshnag, is most polluted in June to August, the yatra months, a Kashmir University study found. Geologist Shakil Romshoo, in a report, maintained that the affected rivers supply about two million people. The same report cited a 2015 study finding July visitor flow in Pahalgam was almost four times its tourism carrying capacity. A road will add vehicles, debris and permanent camps to the same catchment.

Chopan and Bakarwal herders hold customary grazing rights in the meadows around Sheshnag and Panchtarni. The 2017 study documented one family left with a strip between the camp and the lake, without compensation. The DPR's social screening covers only villages along the brownfield road.

The alternative is not an end to the pilgrimage. Uttarakhand limits visitors at Gangotri and Gaumukh. The Kailash Mansarovar yatra restricts repeat trips. Sengupta proposed batches, caps and a shorter season. Writing in July, Mubeen Ahmed Shah argued that the yatra's ecological carrying capacity has never been studied independently or in public. He noted that Gulmarg, Pahalgam and Sonamarg face such studies, while the yatra does not.

Questions the government has not answered

The BRO's statement asks the public to take compliance on trust. These questions would settle it:

1.     Is the Sheshnag work part of NH-501, or a separate BRO job? Which agency ordered it, and under what sanction?

2.     Has forest land been diverted at Sheshnag? If so, under which approval, or under the 2023 border-area exemption?

3.     Was the State or National Board for Wildlife consulted, given the Overa-Aru and Thajwas eco-sensitive zones?

4.     Has anyone assessed glacial-lake outburst risk before cutting slopes at a lake on the government's own high-risk list?

5.     What width is "prescribed", by whom, and where is the excavated debris going?

6.     Will the DPR and any environmental assessment for the Chandanwari–Baltal stretch be made public?

The BRO says its purpose is the pilgrims' safety. There is no public disagreement over that in Kashmir. The Mirwaiz said Kashmir has always welcomed the pilgrims. The dispute is over whether a highway past a high-risk glacial lake, built without public appraisal, makes anyone safer. Thirty years ago, the government's own inquiry chose limits over a road.

(Documents reviewed here include: Redecon (India) Pvt Ltd for NHIDCL, Detailed Project Report for 2/4 laning of Khanabal to Baltal section on NH-501, Volume I – Main Report, January 2024; Jammu Kashmir Coalition of Civil Society and EQUATIONS, Amarnath Yatra: A Militarized Pilgrimage, March 2017.)